Working-day count for a 90-day project

Counting working days for a 90-day project across holiday periods.

The conversion

90 calendar days contains about 64 weekdays, less any holidays inside the window. If the project crosses Spring Festival, that drops to around 59 working days.

The planning error

Teams plan a 90-day project as three working months. It is not — it is two and a half at best, and less across a holiday.

The fix

Plan in working days from the start, with the holiday list applied. Then set milestones on specific working-day counts rather than on calendar dates.

The reporting

Report progress against working days consumed, not calendar days elapsed. Otherwise a holiday looks like underperformance and a busy month looks like acceleration.