Approval cycles in working days: how long Chinese government and corporate approvals actually take.

The pattern

Government and corporate approvals are usually stated in working days — 20 working days for a permit, 5 for a certificate. Those statements are calendar-relative and holiday-affected.

The compounding

An approval quoted at 20 working days is about four calendar weeks in normal periods and six when a holiday block falls inside. Approvals rarely complete faster than stated.

The planning advice

Treat the stated period as a floor, not an estimate. Ask for the basis (working or calendar), then convert and add buffer for holiday content.

The practical use

For anything time-critical, ask when the application window closes rather than when approval will arrive — the closing date is what constrains you.