Calculating a 30 working day lead time

A worked calculation of a 30-working-day lead time into a real calendar date.

The method

Start at the confirmed order date, count forward one working day at a time, skipping weekends and holidays and adding make-up workdays.

A worked case

Order confirmed 20 November 2026. Counting 30 working days lands around 31 December 2026 — because the range contains no public holidays, the count is essentially six calendar weeks.

If it crosses a holiday

The same 30 working days starting 1 January 2027 crosses Spring Festival in February and lands in early March — about nine calendar weeks.

The lesson

The lead time is stable; the calendar date is not. Quote working days internally and calendar dates to customers, recalculated per order.