Using calendar days for a working-day promise
The mistake of promising a working-day lead time as calendar days.
The mistake
A supplier says 30 working days. The buyer promises the customer 30 calendar days. The goods arrive a week to three weeks late, depending on holidays.
The conversion
30 working days is about 42 calendar days in a normal period, and 55+ if it crosses Spring Festival.
Why it happens
Working days sound like days. The unit difference is invisible unless someone converts it, and in a busy sales cycle nobody does.
The fix
Convert every supplier lead time to a calendar date at the moment of quoting your own customer. Then add buffer for holiday content in the window.