Monthly capacity planning with working days
Capacity planning by working days: why monthly counts beat annual averages.
The unit of capacity
Factory capacity is output per working day. Monthly capacity = working days × daily output. An annual average hides the months where the multiplier collapses.
The February problem
A factory with 21 working days in a normal month and 14 in February cannot make up the difference later without overtime or a second shift. Annual planning that assumes 12 equal months always misses.
The method
- Get the monthly working-day count for the year
- Multiply by realistic daily output per line
- Set delivery commitments against the actual monthly figure
- Flag the low months explicitly in the production plan
The practical result
Capacity planning that accounts for working days typically reveals its own shortfall before the orders arrive — which is the point of planning.