Business Days

Working days lost to Spring Festival

How many working days Spring Festival actually costs, including the ramp.

The official loss

The national block removes about five working days. That is the figure in the calendar and the least accurate part of the answer.

The real loss

Add the ramp-down before the block, the shutdown itself, and the ramp-up afterwards. For manufacturing the practical loss is 15–25 working days.

The calculation

ComponentWorking days
Ramp-down2–4
Official block~5
Extended shutdown5–10
Ramp-up4–6
Total15–25

The planning consequence

Spring Festival consumes roughly a month of production capacity. Any annual plan that treats it as a holiday week will miss its numbers.

Need a count instead of the theory? Use the China business days calculator to get working days between two dates, with weekends and public holidays removed.

All articles