Working days vs calendar days in contracts
Working days versus calendar days in commercial contracts: how to draft clearly.
The risk
A contract stating "30 days" without a basis leaves room for two readings, and the difference across a holiday period can be three weeks.
The drafting options
- Use calendar days with a stated holiday carve-out
- Use working days with an attached holiday list
- Define which party's calendar applies
- Specify whether the trigger date is inclusive
The recommended default
Calendar days with an explicit extension for specified holidays. It is unambiguous, verifiable after the fact, and easier to administer than a moving working-day count.
The commercial reality
Ambiguity is resolved by whoever has more leverage when the dispute arises. Drafting it out in advance is cheaper.