Calculating a delivery date from a lead time

Turning a working-day lead time into a delivery date you can commit to.

The chain

Order confirmation date + production lead time + inland transport + freight transit + destination clearance = delivery date. Each leg has its own basis — working or calendar days.

Where dates slip

The buffer rule

Add a buffer proportional to the holiday content of the window. A cross-holiday order needs two to three weeks; a normal one needs three to five days.

The commitment

Commit to the buffered date. An early delivery is good news; a late one is a dispute.