Factory shutdown and working days
Factory shutdown versus the national working-day calendar: two different measures.
The gap
The national calendar says the holiday block is about eight days. Many factories close for two to three weeks, and run below capacity for another week after reopening.
Why they diverge
Workers travel far and return in waves. A factory cannot produce without them, so its effective capacity loss extends well beyond the official block.
The calculation
Effective lost production = shutdown days + ramp-down days + ramp-up days at partial capacity. On a 21-day month, that can be the entire month.
The rule
Use the working-day calendar for office functions; use the factory shutdown calendar for production planning. Never substitute one for the other.