Holiday-adjusted delivery promise

How to build a delivery promise that survives the Chinese holiday calendar.

The method

Start from the calendar date, then subtract the holidays inside the window from the available working days, then extend the date by the shortfall.

A worked case

A 25-working-day lead time starting 1 January 2027 loses about five working days to Spring Festival, so the promise moves from early February to mid-February — before transport is added.

The buffer

Add buffer for the ramp-down and ramp-up, which the calendar does not show. Two weeks is a common figure for anything crossing Spring Festival.

The communication

Tell the buyer which holidays affect the promise and by how much. A transparent date is accepted; an optimistic one is remembered when it slips.