Inspection scheduling around holidays
Scheduling third-party inspections around Chinese holidays without losing the shipment window.
The constraint
Inspection agencies work on business days and book up during the pre-holiday rush. Booking late means an inspection date after the freight cut-off.
The sequence
- Confirm production completion date with the factory
- Book inspection 2–3 weeks ahead
- Leave at least 3 working days between inspection and cut-off
- Allow time for re-inspection if defects are found
The holiday effect
In the two weeks before Spring Festival, inspection slots disappear. Factories also push completion to the last moment, compressing the window further.
The rule
Book inspection when you place the order, not when production finishes. The slot, not the factory, becomes the constraint around holidays.