Missing the pre-holiday ramp-down
The ramp-down before Chinese holidays: the invisible capacity loss.
What happens
In the one to two weeks before a major holiday, workers leave early to travel. Output declines gradually rather than stopping on a date.
Why plans miss it
Calendars show a clean boundary: working until the holiday, closed during it. Reality shows a fade. Orders promised "before the holiday" are produced at reduced staffing.
The effect on quality
Rushed pre-holiday production also carries higher defect risk, because the same work is compressed into fewer hands.
The fix
Treat the last week before a major holiday as 50–70% capacity, and schedule inspection before that window rather than inside it.