Planning production around a holiday calendar
How to plan production against the Chinese holiday calendar for a full year.
The annual sequence
- November: get next year's holiday arrangement
- December: place orders that must ship before Spring Festival
- January: final pre-holiday shipments
- February: expect low output
- March–September: normal planning
- October: National Day adjustment
- November–December: next cycle
The two anchors
Spring Festival and National Day drive the year's two logistics distortions. Everything else is minor by comparison.
The review point
Re-check the calendar in November when the official arrangement is published. Plans built on estimates need updating once facts arrive.
The pairing
Use this with the factory shutdown calendar for production and the holidays tool for the official dates.
Need a count instead of the theory? Use the China business days calculator to get working days between two dates, with weekends and public holidays removed.