Business Days

Effective production days per year

Effective production days per year in China after holidays and ramp effects.

The base

About 250 national working days per year, after weekends and statutory holidays.

The adjustment

Subtract the extra capacity lost around Spring Festival beyond the official block — roughly 10–20 days — and add overtime if the factory runs extra shifts.

The effective figure

Effective production days commonly land around 230–240 for a typical factory, or lower where Spring Festival is long.

How to use it

Use 235 as a working assumption unless you have the factory's own calendar. Then replace it with their actual dates for anything contractual.

Need a count instead of the theory? Use the China business days calculator to get working days between two dates, with weekends and public holidays removed.