Why lead times are quoted in working days
Why Chinese suppliers quote lead times in working days, and how to convert them.
The reason
Working days describe available production time. Quoting in calendar days would penalise the supplier for weekends and holidays that do not change what the factory can actually do.
The conversion
Divide the working-day lead time by roughly five, then multiply by seven to get calendar weeks — then add any holiday block that falls inside the window.
The worked example
A 30-working-day lead time is about six calendar weeks. If it crosses Spring Festival, it can stretch to eight or nine weeks.
The buyer's rule
Always ask which basis the lead time uses, and always convert before promising a date to your own customer.